Project Summary
No of Housing Units /Beneficiaries | 356 |
TEC with VAT (Rs. Mn)(Revised) | |
Target Beneficiaries | |
Location of Housing Project | Land called “Old Thanayam Idama” located at Moratuwa Municipal Council area |
Commencement of Construction | July, 2012 |
Target Date of Completion of Construction (Revised) | 31st December, 2016 |
Typology | G+11 |
Size of a housing unit | 456 sq. ft.(Exclusive of open area) |
Budgetary Allocation – 2016
(Rs. Mn) |
340.00 |
Cumulative Progress as at 31.08.2016
Physical Financial (Rs. Mn) |
75%
927.375 |
Current Status | Ø Construction is in progress
Note: Expected targets could not be achieved due to inadequate manpower assigned for the project by SEC. At the end of the year 2015 the balance unutilized funds of Rs. Mn 90.00 was transferred to Model Village Programme of NHDA on the instruction of Hon. Minister. |