Angulana “Sayurupura” Housing Project | |
Dismantling of Existing Elevator and Supply, Installation, Testing & Commissioning of Passenger Elevator | |
Estimated Cost | Rs.Mn. 20.22 (including tax) |
Source of Funds | GOSL |
Project Period | 2025 – 2026 |
Contractor | Trade Promoters (Pvt) Ltd |
Contract Amount | Rs. Mn. 14.89 (including tax) |
Commencement Date | 23.02.2026 |
Target Completion Date | 22.08.2026 |