Dismantling of Existing Elevator and Supply, Installation, Testing & Commissioning of Passenger Elevator at Sahaspura Housing Project

SAHASPURA  HOUSING PROJECT

DISMANTLING OF EXISTING ELEVATOR AND SUPPLY, INSTALLATION, TESTING & COMMISSIONING OF PASSENGER ELEVATOR
Estimated CostRs.Mn.  20.22  (including tax)
Source of FundsGOSL
Project Period2025 – 2026
ContractorTrade Promoters (Pvt) Ltd
Contract AmountRs. Mn. 14.89 (including tax)
Commencement Date23.02.2026
Target Completion Date22.08.2026